Wednesday 20 February 2013

20.02.13 - Doors are on . . .

It has been a busy week. Lots of phone calls and discussions about paint and tiles and carpentry and doors . . . the carpenter has put up the majority of the architraves, skirting boards, window trims etc and doorways are in and the doors have been hung, they still need to be painted.  But we think they are fantastic!

Front door . . .

BIR in Bedroom 2


Bathroom door and Laundry broom cupboard behind . . .

Bedroom 3 & 4 . . .



So the carpenter will finish soon then the tiler will start next week, followed by interior painting, then the kitchen goes in . . .  







Friday 15 February 2013

15.02.13 - Bag and Paint . . .

Wow . . . we had a phone call from our painter today asking us if we had seem our house lately... 'no' ... 'well you best get out here and take a look, it is gorgeous'.
And it is indeed. We are a little (a lot) excited now!

Panorama pic of our gorgeous bagged and painted house . . . 

Front . . . love it!

Front door, to be stained same as wooden beams.

All our internal doors and door frames have arrived.
Panorama pic of the back of the house . . .


Next week - the internal painting will happen, final wood work fixtures, door frames and doors go in... then the tiling begins!





Monday 4 February 2013

03.02.13 - We have walls and wooden beams . . .

Wow!! We went out to the house yesterday not expecting much to have changed and we were blown away...

The gyrocking on the internal walls is all but done and we have some beautiful timber beams to the front porch . . .  and corbeling/trim around the front windows.

Now we are really getting excited!!
Wooden beams have been installed on the front porch. . .  love them!! 

Looking from living room window to the dining area . . .

From the kitchen looking into the living room . . .

Love how the front is taking shape . . .