Wednesday 20 February 2013

20.02.13 - Doors are on . . .

It has been a busy week. Lots of phone calls and discussions about paint and tiles and carpentry and doors . . . the carpenter has put up the majority of the architraves, skirting boards, window trims etc and doorways are in and the doors have been hung, they still need to be painted.  But we think they are fantastic!

Front door . . .

BIR in Bedroom 2


Bathroom door and Laundry broom cupboard behind . . .

Bedroom 3 & 4 . . .



So the carpenter will finish soon then the tiler will start next week, followed by interior painting, then the kitchen goes in . . .  