Met the Site Supervisor at the house today to go over a few things -
- kitchen, laundry, ensuite, bathroom, powder room cupboards all get fitted in tomorrow
- plasterer back in to finish off tomorrow
- painting of interior starts Wednesday.
- stone bench tops will be measued up this week
- kitchen splashback will also be measured this week
It's going to be a very busy week for the tradies, then for 2 weeks lots of little things happen.
First week of April flooring will be laid . . . then - it will be about 3 weeks before we get the keys!!
|  | 
| Ensuite tiling completed - the entire room is dark brown tiles, but in this pic it looks like 2 different colours (it isn't) when the light hits it. | 
|  | 
| Ensuite tiles - they are actually a dark brown (the true colour is nothing like this) | 
|  | 
| This is better - shows the dark brown tiles | 
|  | 
| Bathroom - vanity (true colour) | 
|  | 
| Bathroom - shower recess (true colour) | 
|  | 
| Powder room | 
|  | 
| Laundry... | 
All cupboards for the tiled areas are being fitted tomorrow . . .  excited - very much! 
 